Partnering with the Phantom

November 2017 | Source: Indian Management
0 8 0.0/5

Is Quality Popular? In theory Perhaps Not in practice

Is quality a fully delegable responsibility? No.

What are the challenges to muster support for a specific quality initiative?

The key one is that upper managers believe that quality  improvement project offer lesser tangible rewards that other proposals.

Dr J M Juran taught us to “scare up” support for quality initiative. He advised: speak the language of upper manager-“money” Although a quality improvement project may not directly influence revenues,

It can dramatically reduce wasteful costs. These wasteful costs are the Costs Of Poor Quality (COPQ).

These are traceable to a phantom factory within the factory dedicated to meticulously manufacturing waste.

An owner of a reputed textile mill in Mumbai challenged my thesis: over 25% of total costs are COPQ in a Textile mill. I asked three leading Questions:

  • Do you receive customer complaints?
  • Do you have incoming inventory?
  • Do you have dormant inventory?

The owner and I invested time in stratifying customers” complaints: curry stains, rust marks, pigeon dropping, selvedge cut, short length, fading blue, etc. Each complaint cost more than others. That lost material, additional effort, and delivery delays were estimated in a COPQ table.

The Owner also mentioned that some English customers had reduced their order sizes, preferring to purchase from Hong Kong.

On prioritizing the complaints based on frequency enemy #1 was pigeon droppings.

The Pareto based on COPQ identified a completely  different enemy. Packaging. Goods that conformed (did not have more than 12 major defects and more than 10 minor defects per 400 meters) to specifications at dispatch were unfit for use on arrival at the customer site. Based on the volume to be dispatched, the outsourced transport agency would use appropriate-sized trucks but of variable.

The COPQ alarm was even greater at incoming inventory. Further, the ineffective sales forecasting system burdened the mill with dormant inventory.

Shocked with this validated information, the owner wondered if he could double his profit without investing, partnering with the phantom! Could he think otherwise? As a consequence, the owner organized an executive briefing where he narrated his experience to the upper managers.

As par the phantom’s instruction, at subsequent monthly quality council meetings, the owner bolted the meeting room from inside at the dot of 8 am. Did he love this?!

Lessons learned

  1. ‘Scare up’ support for quality initiative, using the language of upper manager-‘money’
  2. COPQ is managed by a phantom factory within the factory
  3. Dipstick for COPQ measurement: customer complaints and incoming inventory
  4. Upper Managers see the waste with their own eyes
  5. Perceived enemy #1 is not necessarily the actual enemy #1
  6. Processes that are not owned, such as logistics, can damage products that conformed to specifications
  7. Quality Council meetings should not be a COPQ
CREDITS: Suresh Lulla, Founder & Mentor, Qimpro Consultants Pvt. Ltd.